Sha Tin Sewage Treatment Works

Service provided:
14 monitoring arrays of 3D deformation and angular distortion to the structural stability of the cavern.
Location:
Sha Tin, Hong Kong SAR
Period of the service:
July 2021- ongoing
Sixense expertise used:

Not In My Backyard

In an effort to relocate a series of public facilities to caverns, the HKSAR Government commissioned the creation of a new cavern for the Sha Tin Sewage Treatment Works (STSTW). Releasing 28 hectares of land, the project will enable a much more effective use of the overground land.

The aging treatment works not only occupies valuable land, but also falling behind on treatment capacity against the new town’s population growth. In addition to freeing the land, relocating the works will increase its capacity and efficiency, allowing the the sewage treatment process to become much more effective.

Carving A Way Through

The construction works was commenced in February 2019, and the whole project is expected to be completed in the year of 2031. Blasting was utilized to carve the access tunnel, as well as the body of the cavern in solid rock.

Sixense was contracted to install a total of 14 instrumentation arrays to closely monitor the structural stability of the cavern. The arrays were designed to show the 3D deformation, angular distortion, as well as the convergence of the newly created structure, as blasting is both a high-impact and a high-risk construction method.

Swift and Steady

 

Sixense provided experienced technicians and engineers to help install the monitoring arrays on the selected sections of the cavern walls. Instrumentation an array include: load cells, vibrating-wire strain gauges, vibrating-wire piezometers, multi-point borehole extensometers, and door-stopper strain gauges. We produced custom data-loggers especially modified for this project, enabling real-time transmission of the monitoring data from all the sensors.

We continuously adopt the arrays to the needs of our Client, re-configuring each array over the monitoring period as the blasting operations went on. Sensors in such a tough environment are especially high-maintenance, so we put safety precautions in place to help our sensors survive the impact, and to make sure that they function to record the blasting events.

 

Images of the project

14

Monitoring Arrays

14

Custom Programmed Dataloggers

70

Load Cells

70

Vibrating-wire Strain Gauges

56

Vibrating-wire Piezometers

70

Multi-point Borehole Extensometer

56

Doorstopper Strain Gauge

Tags

Extensometer Vibrating-wire Piezometers Strain Gauge Cavern Monitoring Urban Utilities Underground